Own right of the debtor to exercise the remedies

Com. September 8, 2015 (n°14-14.192) F-PB:

A company and its manager, ordered to pay various sums due to the poor performance of a contract, had appealed against the judgment ten days before the company was put into compulsory liquidation.
The liquidator, summoned for forced intervention by the respondents, had let it be known that he would not constitute himself on behalf of the company for lack of cash. The plaintiffs then criticize the appeal judgment for having rejected their claims directed against the company and its representative. The Court of Cassation dismissed the appeal. According to the Court, it follows from Article L. 641-9 I of the Commercial Code that when proceedings seeking to order the debtor to pay a sum of money for a cause prior to the opening judgment of its judicial liquidation, is in progress on the date of this judgment, the debtor has, in this case, the right to exercise the means of appeal provided for by law against the decision ruling on the application for condemnation.

Nullity of the contract – Impossibility of restitution

3rd Civil . July 8, 2015 (n°14-11.582) FS-PB:

A municipality had granted the real estate civil society (SCI) a real estate leasing contract.
Relying on a failure to pay rent, the municipality obtained by interim order, the finding of the resolution of the contract to the damages of the SCI and the condemnation of the latter to pay it a provision to be worth on the rents due and a monthly occupancy allowance until the premises are vacated. The SCI then sued the municipality for nullity of the leasing contract and reimbursement of the rent paid, on the grounds of the absence of authorization issued to the mayor by the municipal council to conclude such a contract. Finally, the municipality requested the payment of an occupancy allowance for the period prior to the cancellation. The Court of Appeal rejected the municipality's request for the payment of an occupancy allowance for the period prior to the cancellation of the municipality insofar as, due to the restitution of the building, the municipality no did not experience any depletion.
The Court of Cassation quashed the appeal judgment and specified that in the event that a null contract has been executed, the parties must be returned to the state in which they were before this execution and that, when this restoration takes place proves impossible, the party who has benefited from a service that it cannot restore, such as the enjoyment of a leased property, must pay an occupancy allowance.

Contractual obligation and penalty clause

2nd Civil . September 3, 2015 (n°14-20.431) F-PB:

The sellers of a building, have, by authentic deed, subscribed the obligation, to remove a planter established on the public domain, under daily penalty.
An enforcement judge nevertheless declared inadmissible the purchaser's request for the liquidation of the contractual penalty. The latter having ordered, under the notarial title, a seizure-sale and two seizures-attribution, to obtain payment of the agreed sum, the sellers seized an execution judge, who rejected their request for cancellation of the order seizure-sale, release of the two seizure-attribution and cancellation of the penalty. To cancel the seizure order and order the release of the two attachments, the trial judges held that no penalty payment could give rise to a measure of forced execution before its liquidation, that this penalty be pronounced by a judge or that it is agreed between the parties in an act to ensure the execution of an obligation to do.
The Court of Cassation first recalls that the judge must give or restore their exact qualification to the facts and acts in dispute without stopping at the name that the parties would have proposed. Consequently, it was up to the Court of Appeal to qualify and assess the disputed clause, which in this case amounted to a penalty clause.

Indivisibility

1st Civil . September 10, 2015 (No. 14-13.658 and No. 14-17.772) FS-PBI:

The two judgments presented here relate to similar facts.
In each of the cases, a bank challenges before the Court of Cassation the decision of the Court of Appeal pronouncing the nullity of a contract for the sale and installation of a wind turbine as well as the nullity of the loan contract granted in order to fund this acquisition. The Court of Cassation dismissed both appeals.
The Court, in support of its first judgment, held that the Court of Appeal had noted that the credit offer was assigned to the main contract and had been informed by the seller, and that the lender had returned the borrowed funds in the hands of the latter, which characterized the existence of conventional indivisibility between the sale and loan contracts within the meaning of Article 1218 of the Civil Code. In the second judgment, the Court considers that the trial judges highlighted the indivisibility of the disputed contracts by stating, on the one hand, that the credit agreement was ancillary to the contract of sale to which it was subordinated, and on the other hand, that the borrower had attested to the performance of the main contract in order to obtain the release of the funds by the lender, who had made them available to the seller. Consequently, the resolution of the main contract entailed the annihilation of the ancillary contract.

Conditions of participation in decisions in a real estate civil society

3rd Civil . July 8, 2015 (n°13-27.248) FS-PB:

The Court of Cassation recalls that under the terms of article 1844 of the civil code, only the partners have the right to participate in the collective decisions of the company.
Thus, the Court confirms the appeal ruling pronouncing the nullity of a general meeting in which the heirs of a deceased partner took part and during which they participated in the appointment of the manager when they did not could claim neither approval nor the status of associate.

Abuse of majority

3rd Civil . July 8, 2015 (No. 13-14.348) FS-PB:

The minority shareholder of an SCI sued the majority shareholder to have several decisions taken by the general meeting declared null and void.
Indeed, this SCI, initially set up to acquire and operate a building, had sold two-thirds of its shares to a company. Then, following this new distribution of shares, a capital increase had been voted and fully subscribed by the majority shareholder, the corporate purpose had been modified and all of the results of two financial years had been allocated to reserves. The Court of Appeal having concluded that the statutory rules of reinforced majority required for the modification of the statutes had been disregarded, it sanctioned these irregularities by nullity.
The decision of the judges on the merits is confirmed by the Court of Cassation on the grounds that the principle of unanimity, unless otherwise stipulated, to modify the statutes, laid down by article 1836 of the civil code, falls under the mandatory provisions of the title referred to in the article 1844-10 of the same code.

French